Advertisement

Rainbow Valley Bridge work wrapping up on Whitemud Drive

Traffic flowing again on both spans of the Rainbow Valley Bridge on Whitemud Drive. August 23, 2026. Global News

After two and a half years of near-daily gridlock on Whitemud Drive in southwest Edmonton due to road construction, the light at the end of the tunnel — or bridge, actually — is near.

This past weekend, the newly expanded and upgraded eastbound Rainbow Valley Bridge reopened to traffic.

That bridge had been closed for just over a year, as part of Stage 2 of the Terwillegar Drive expansion project, and came after the westbound bridge underwent the same upgrade work.

In February 2024, the westbound lanes of the Whitemud over the north bridge were closed and two-way traffic was redirected to the eastbound lanes on the south bridge.

During that time, the city rehabilitated and widened the north bridge to four lanes plus shoulders and added a new pedestrian/cyclist bridge beside it.

Story continues below advertisement

Last August, the city shifted traffic over to the completed bridge and began similar construction work on the eastbound span.

Click to play video: 'Traffic disruptions expected along Whitemud Drive due to Rainbow Valley Bridge construction'
Traffic disruptions expected along Whitemud Drive due to Rainbow Valley Bridge construction

That work is now largely finished, marking the completion of major bridge work for Stage 2 of the Terwillegar Drive Expansion project.

Get breaking Canada news delivered to your inbox as it happens so you won't miss a trending story.

Get breaking National news

Get breaking Canada news delivered to your inbox as it happens so you won't miss a trending story.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

Three eastbound lanes are now available on Rainbow Valley Bridge. There are still some traffic reductions on the westbound side, with two lanes open between 122 Street and 142 Street (over the bridge), increasing to three lanes after the turnoff to Terwillegar Drive southbound.

Once the full project is completed this fall, the city said the widened bridges will provide four lanes of traffic in each direction.

Landscaping and site restoration work will continue through 2027, the city added.

Story continues below advertisement

The Terwillegar Drive Expansion project started in 2021 and involved upgrading Terwillegar Drive to an expressway instead of a light-free freeway, which would have cost more.

The work at the Whitemud also included adding an new 142 Street pedestrian bridge linking the Brookside and Bulyea Heights neighbourhoods, as well as a multi-use pedestrian bridge adjacent to the Rainbow Valley vehicle traffic bridges.

Phase 3 of the project includes further road widening, upgrades to the Terwillegar Drive interchanges over Anthony Henday Drive (already underway) and adding dedicated transit lanes and a shared-use path.

Click to play video: 'Heavy traffic gridlocks in southwest Edmonton as several construction projects ramp up'
Heavy traffic gridlocks in southwest Edmonton as several construction projects ramp up

The six-kilometre expressway project is expected to be finished in 2028.

The city was initially planning in 2017 to expand the road into a freeway, as the road was built in the 1980s with future free-flow in mind.

Story continues below advertisement

However as the estimate cost exceeded $1 billion, city council in 2018 scaled back the plan to an expressway with the existing light-controlled intersections remaining in place.

Sponsored content

AdChoices