New crane brought in to help remove toppled crane in Halifax

Click to play video: 'New crane brought in to ensure removal of toppled crane done safely'
New crane brought in to ensure removal of toppled crane done safely
WATCH: There are a lot of moving parts to ensure the removal is done safely, and to help with that a new crane is now set up in the area. Alicia Draus has more – Oct 6, 2019

Post-tropical storm Dorian brought down a construction crane in downtown Halifax, and the crane still remains where it fell nearly a month later.

In early September, the crane toppled over a building under construction on South Park Street in Halifax.

READ MORE: Province renews emergency order for crane removal in Halifax

Engineers from Harbourside Engineering Consultants and R&D Crane Operator Limited say there are a lot of moving parts to ensure the removal is done safely, so to help with that a new crane was set up in the area over the weekend.

However, they’re still not ready to start that process as work is still ongoing to strap down and stabilize the collapsed crane. Once that is complete the new crane will be one of two that will be used to lift up the middle section of the tower off the building.

Story continues below advertisement

READ MORE: N.S. government hires 2 companies to help remove collapsed construction crane

It weighs about 30,000 kg, and two cranes will be required because of how far away the tower is from the roads where the removal cranes can be set up.

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.

Get breaking National news

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

The surrounding area of the crane was closed off under an emergency order by the province on Oct. 2 to ensure the safety of those in the area as work continues to remove the crane.

Click to play video: 'Localized state of emergency extended in near crane site'
Localized state of emergency extended in near crane site

The localized emergency area is defined as the city block within the boundaries of Cathedral Lane, Brenton Street, Brenton Place and Spring Garden Road.

Story continues below advertisement

However, the closed off section of South Park Street has been slightly expanded to accommodate the new crane, so pedestrians will no longer be able to cross South Part Street at Brenton Place.

Meanwhile Halifax Water crews were also on scene Sunday. Contractors had asked Halifax Water to be ready in case something goes wrong with the water pipes, fearing the weight of the new crane could damage pipes underground.

“We were asked to be at the ready to shut down a water valve if that was required. But when our crews got down there this morning to do that work they realized the valve was actually malfunctioning so they had to shut down the water to do the repair,” said James Campbell, a spokesperson for Halifax Water.

Campbell said the water was restored to the area mid afternoon.