Menu

Topics

Connect

Comments

Want to discuss? Please read our Commenting Policy first.

Keystone XL pipeline builder asks U.S. judge to allow some pre-construction work

Piping to be used for the Keystone XL pipe line from Cushing, Oklahoma to the Gulf of Mexico sits stacked at a storage yard at TransCanada Pipe Yard near Cushing, Oklahoma, USA, 21 March 2012 (reissued 09 November 2018). File photo/Canadian Press

The company that wants to build the Keystone XL pipeline is asking a judge to change his order blocking the project to allow pre-construction work to continue, such as purchasing materials and finalizing contracts.

Story continues below advertisement

Attorneys for the company will argue in a Wednesday telephone conference that U.S. District Judge Brian Morris should clarify or amend his ruling to say the injunction does not apply to activities such as finalizing contracts, purchasing materials, conducting land surveys and discussing federal permits.

READ MORE: Keystone XL pipeline blocked by federal judge in Montana, throwing project’s future into doubt

TransCanada wants to keep that preliminary work on track so that the Calgary-based company can be prepared to start pipeline construction as early as mid-February.

Blocking the pre-construction work even for several weeks would likely cause the company to miss the entire 2019 construction season and delay its 2021 target for oil to start flowing through the pipeline.

“A one-year delay in construction of the pipeline would result in substantial harm to TransCanada, as well was to United States workers, and to TransCanada’s customers relying on the current in-service date of the project,” TransCanada Pipelines Limited Senior Vice-President Norrie Ramsay said in a written statement to the court.

Story continues below advertisement

A year-long delay would cost TransCanada $949 million in earnings and put off the hiring of about 6,600 workers for construction, Ramsay said.

READ MORE: Additional environmental assessment ordered for Keystone XL pipeline

On Nov. 8, Morris blocked TransCanada’s permit to build the pipeline from Alberta’s oilsands through a half-dozen U.S. states to the Gulf of Mexico.

The judge had ruled the Trump administration had not fully considered the environmental effects of the pipeline.

READ MORE: Donald Trump gives the green light to ‘incredible’ Keystone XL pipeline

TransCanada’s attorneys say the company is considering appealing Morris’ order. Ramsay also estimates that it could take as long as the first quarter of 2019 for federal agencies to complete the review that Morris ordered.

One group that sued to block the pipeline project, the Northern Plains Resource Council, declined comment on TransCanada’s request, spokesman Dustin Ogdin said.

Story continues below advertisement

The attorney for another plaintiff, Indigenous Environmental Network, did not respond to a voicemail requesting comment.

Advertisement

You are viewing an Accelerated Mobile Webpage.

View Original Article