CALGARY – The first phase of Imperial Oil Ltd.’s Kearl oilsands mine is nearing completion, with all of the gargantuan pieces of equipment having finally made their way from South Korea to Alberta, the company’s CEO said Wednesday.
Bruce March told the TD Securities Energy Conference the $10.9-billion mine is now 92 per cent complete and on track to start up later this year.
Calgary-based Imperial (TSX:IMO), which is majority-owned by U.S. energy giant ExxonMobil (NYSE:XOM), ran into legal trouble transporting giant modules manufactured in Korea to Alberta through the United States.
The enormous shipments moved across the Pacific and along rivers to Lewiston, Idaho, where they were to be transported by truck the rest of the way to northern Alberta.
Get weekly money news
The initial plan was to move the shipments along two-way highways through Idaho and Montana, but legal challenges arose because local residents and conservation groups didn’t want the megaloads moving along those scenic routes.
Eventually, Imperial broke up the loads into smaller parts and applied to ship the equipment along Interstate highways instead.
“They’re all in Alberta as of May. We’ve got about 20 modules that have to still be reassembled in Edmonton. They will be complete by about mid-July,” March told reporters on the sidelines of the conference.
- Alberta tweaks carbon capture incentive program to allow grants during construction
- ‘Cash is king’: Why money is a popular holiday present for many Canadians
- Rancher says Alberta well cleanup fund a positive step — but litany of concerns remain
- What makes the Anthropic IPO so significant, and what is the ‘god share’?
For the next $8.9-billion phase of Kearl, which is set to start up in 2015, March said Imperial has set aside space at fabrication yards in Edmonton to construct the modules.
Longer term, Imperial is eyeing a property just south of Kearl called Aspen for a possible new project that will use high-pressure steam pumped deep underground, instead of open-pit mining, to extract the bitumen.
“It’ll probably come in two 40,000 barrel a day stages in the decade of 2020 and beyond,” said March.
Imperial has vast steam-driven oilsands operations at Cold Lake, a 25 per cent stake in the Syncrude Canada oilsands mine, a handful of refineries across Canada and a chain of Esso-branded fuel stations.