First Nation wants reasons for Trans Mountain ruling; says it’s entitled to appeal

In this photograph taken with a drone, workers lay pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023. A B.C. First Nation is asking the Canada Energy Regulator to release its reasons as soon as possible for allowing a modification of the Trans Mountain pipeline's route. THE CANADIAN PRESS/Darryl Dyck

A B.C. First Nation is asking the Canada Energy Regulator to release its reasons as soon as possible for allowing a modification of the Trans Mountain pipeline’s route.

In a letter to the regulator dated Wednesday, a lawyer representing the Stk’emlupsemc te Secwepemc Nation (SSN) said the decision to grant the route deviation Monday without providing its reasons has left the First Nation without the ability to decide its next steps.

The letter said the First Nation has the right to request a reconsideration of the decision, or to appeal it through the Federal Court of Appeal.

“This has, in fact, created significant uncertainty for SSN and left SSN without the procedural options that would otherwise be afforded to it with the potential for irreparable harm to its rights and title as a result,” the letter states.

The Canada Energy Regulator ruled Monday to allow Trans Mountain Corp. to alter the route slightly for a 1.3-kilometre stretch of pipeline in the Jacko Lake area near Kamloops, B.C.

Story continues below advertisement
Click to play video: 'Trans-Mountain Pipeline faces hearing over construction around sacred lake'
Trans-Mountain Pipeline faces hearing over construction around sacred lake

It said it would release its reasons for the decision in the coming weeks.

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.

Get daily National news

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

Trans Mountain Corp, a Crown corporation, had requested the change because of what it said were engineering difficulties in the area related to the construction of a tunnel.

The company had warned that being forced to stick to its original route and construction method could result in up to a nine-month delay in the pipeline’s completion, as well as an additional $86 million more in project costs.

Trans Mountain had been hoping to have the pipeline completed by early 2024.

But the Stk’emlupsemc te Secwepemc Nation, whose traditional territory the pipeline crosses and who had only agreed to the originally proposed route, opposed Trans Mountain’s application.

Story continues below advertisement
Click to play video: '‘This project has been seriously mismanaged’: The factors driving up Trans Mountain pipeline expansion costs'
‘This project has been seriously mismanaged’: The factors driving up Trans Mountain pipeline expansion costs

The First Nation has said the new route threatens to disturb land that has spiritual and cultural significance.

The First Nation’s lawyer said in the letter Wednesday that Trans Mountain has indicated it wants to break ground on the new route on Oct. 2.

The Trans Mountain pipeline is Canada’s only pipeline system transporting oil from Alberta to the West Coast. The expansion, which is currently underway, will boost the pipeline’s capacity to 890,000 barrels per day (bpd) from 300,000 bpd.

The pipeline — which was bought by the federal government for $4.5 billion in 2018 after previous owner Kinder Morgan Canada Inc. threatened to scrap the expansion project in the face of environmentalist opposition and regulatory hurdles — has already been plagued by construction-related challenges and delays.

Its projected price tag has also soared: first to $12.6 billion, then to $21.4 billion and most recently to $30.9 billion.