NYC transit chief slams Bombardier, halts rail car deliveries over problems

A file photo of Bombardier commuter trains. Darryl Dyck/The Canadian Press

The head of the New York City Transit Authority and former chief executive at the Toronto Transit Commission says he is having “déjà vu times two” with problems around trains from Bombardier Inc.

READ MORE: Bombardier cutting about 5,000 jobs as part of restructuring plan

Andy Byford told the state transit authority this week that New York City Transit will halt new train car deliveries until more of the existing cars are fixed.

“It’s gruelling,” Byford said at Metropolitan Transportation Authority committee meeting Tuesday.

“You have to stay on their case, you have to hold their hands, you have to cajole them.”

He cited “depressing” issues with the HVAC system software and past problems with springs between the cars and doors that were “weeping oil.”

Story continues below advertisement

“I’ve been around this cycle now twice with Bombardier — twice in Toronto,” he said, recalling the production delays and defects that plagued streetcar orders during his five years at the helm of Canada’s largest municipal transit authority.

WATCH: Bombardier slashes 5,000 jobs

Click to play video: 'Bombardier Announces More Cuts'
Bombardier Announces More Cuts

“Eventually they get the build quality right and suddenly they start to come off the production line like a well-oiled machine,” he said, adding that “you end up with a very good product.”

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.

Get breaking National news

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

New York City Transit was expecting 13 of the cars, which cost about $2-million apiece, back from repairs this week following software issues.

READ MORE: Flying Colours completes first trio of Bombardier Challenger 650 medevac interiors

Bombardier said it has delivered 160 out of about 300 cars so far, with some still in testing.

Story continues below advertisement

“We understand the frustration and we own the issue,” spokesman Eric Prudhomme said in an email Thursday evening.

“It’s not unusual in the industry to have some issues, particularly in the early stages of passenger service.”

Prudhomme said he expects the technical problems with the R179 cars, which run on several lines in New York City, to be fixed “shortly,” with 50 employees “working around the clock” at Bombardier’s plant in Plattsburgh, N.Y.

None of the problems has jeopardized passenger safety, the company has said.

WATCH BELOW: Bombardier’s newly built TTC streetcars already being sent back for repairs

Click to play video: 'Bombardier’s newly built TTC streetcars already being sent back for repairs'
Bombardier’s newly built TTC streetcars already being sent back for repairs

New York City Transit has representatives on site monitoring the progress, on top of bi-weekly meetings to discuss vehicles that were delivered but not fit for service, Byford said.

Story continues below advertisement

“Short of actually building the damn things, we’re doing everything else that we possibly can do,” he said.

READ MORE: Bombardier says business jets unaffected by diplomatic skirmishes with China, Saudi

Earlier this month, Swiss Federal Railways opted to stop taking new trains from the Montreal-based company until it fixes the ones already in service.

Bombardier is also facing a Feb. 1 deadline for delivery of the first six of 76 vehicles for Toronto’s Crosstown Eglinton light rail line, with one car already at a Metrolinx site in Toronto.