Groups behind Montreal’s new Champlain Bridge say project will be done on time

Click to play video: 'When will the new Champlain Bridge open?'
When will the new Champlain Bridge open?
WATCH: Will the new Champlain Bridge be delivered on time at the end of 2018 or will it be late? Global's Tim Sargeant takes a tour of the construction site to find out more – Feb 23, 2018

The consortium building Montreal’s Champlain Bridge over the Saint Lawrence River is saying it can deliver the new structure on time by December 2018 but it will cost more than the original estimate.

READ MORE: New Champlain Bridge expected to open before Christmas despite rumours of delay

Members of the consortium along with representatives from the federal government and the Crown corporation that manages two of Montreal’s bridges gave an update Friday on the progress of the project.

READ MORE: 2,000 defects found on Montreal’s new Champlain Bridge

They say the new span replacing the Champlain Bridge is 65 per cent complete and the goal of having it ready by the end of the year is realistic and attainable.

Get expert insights, Q&A on markets, housing, inflation, and personal finance information delivered to you every Saturday.

Get weekly money news

Get expert insights, Q&A on markets, housing, inflation, and personal finance information delivered to you every Saturday.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

READ MORE: New Champlain Bridge celebrates one year of construction

The number of workers on the project increased from 650 last summer to 850 in January in order to get work done more quickly and within the scheduled timetable.

Story continues below advertisement

WATCH BELOW: Work on the Champlain Bridge

No one was able to give details on the extra costs of the project, which had an original price tag of $4.2 billion to be paid by the federal government.

READ MORE: Workers on overdrive to finish Montreal’s new Champlain Bridge

The consortium led by SNC-Lavalin risks being fined $100,000 a day for the first seven days past the scheduled completion date and $400,000 a day after that.

READ MORE: Whistleblowing engineer who exposed Champlain Bridge woes faces sanction

The federal government says the precise deadline for the project is currently being negotiated.

READ MORE: Lawsuit filed over Champlain Bridge construction delays

Ottawa is already preparing for a possible delay by setting aside an extra $10 million to reinforce the aging Champlain Bridge in case it has to remain operational until summer 2019.