Menu

Topics

Connect

Comments

Want to discuss? Please read our Commenting Policy first.

Regulator calls out Trans Mountain Corp. for ‘environmental non-compliance’ in B.C.

WATCH ABOVE: (From Jan. 29, 2024) Trans Mountain Corp. says it recently encountered technical issues with the project that could delay its completion. – Jan 29, 2024

The company building the Trans Mountain pipeline expansion has been cited for environmental non-compliance related to its management of recent flooding in B.C.

Story continues below advertisement

The Canada Energy Regulator said Thursday its inspection officers found issues near Abbotsford, B.C., where Trans Mountain Corp. has been working on the final stretch of the multi-year oil pipeline project.

The regulator said the Crown corporation was not properly maintaining a watercourse isolation, wildlife fencing, soil coverings and dewatering pump and sump locations following recent heavy rain.

The regulator has ordered Trans Mountain Corp. to address the environmental deficiencies, develop a water management plan and investigate and report on its environmental failings in the area.

The Trans Mountain pipeline is Canada’s only oil pipeline to the West Coast and its expansion will increase the pipeline’s capacity to 890,000 barrels per day from 300,000 bpd currently.

Construction is more than 98 per cent complete, but Trans Mountain Corp. has been racing against the clock as it deals with a variety of difficulties related to hard rock and challenging terrain.

Advertisement
Advertisement

You are viewing an Accelerated Mobile Webpage.

View Original Article