Menu

Topics

Connect

Comments

Want to discuss? Please read our Commenting Policy first.

Government of Alberta takes 50 per cent stake in Sturgeon Refinery for $825M

WATCH ABOVE: The Alberta government now owns 50 per cent of the Sturgeon Refinery, a facility that has been plagued with delays and cost overruns. But experts say it’s too soon to say whether this is a good deal for taxpayers. Julia Wong reports – Jul 5, 2021

The Alberta government is taking 50 per cent ownership of the controversial Sturgeon Refinery by paying $825 million to reduce tolling costs at the facility northeast of Edmonton.

Story continues below advertisement

The province has signed a restructuring deal that also extends the length of Alberta’s processing contract with the refinery by 10 years, to 2058.

The deal means less taxpayer risk in the long-term and it won’t cost the province any more than it was already obligated to pay as a toll payer, the province said Monday.

The government-owned Alberta Petroleum Marketing Commission has a contract to provide bitumen to the refinery.

READ MORE: Sturgeon Refinery now refining Alberta bitumen

Under the terms of the new deal, the province will pay North West Refining $425 million for its 50 per cent equity stake in the refinery and will pay Canadian Natural Resources Ltd., which will continue to own the other 50 per cent of the refinery, $400 million.

The daily email you need for 's top news stories.

As a result of making the payments now, the province will not have to pay approximately $1 billion in tolling payments over the next 30 years. It will also get to play a decision-making role in the refinery’s operations.

Story continues below advertisement

In a news release, Energy Minister Sonya Savage said the restructuring will benefit Albertans in the long run.

“We are taking action to get a better deal for taxpayers and reducing long-term costs. This agreement provides more economic certainty which will benefit Albertans today and into the future,” Savage said.

READ MORE: Sturgeon Refinery facing more delays after tests, won’t process bitumen until early 2020

Construction was completed on the $9.7-billion Sturgeon Refinery in the fall of 2017 and it was to begin processing as much as 80,000 barrels per day of heavy bitumen in early 2018 after starting up with partly upgraded synthetic crude from oilsands mines.

However, it did not begin processing until 2020 after two years of delays, blamed mainly on equipment failures.

A report from Alberta’s Department of Energy said the Alberta Petroleum Marketing Commission had a $2.68-billion net loss last year due primarily to “onerous” tolling contracts with the Sturgeon Refinery.

Story continues below advertisement

Kathleen Ganley, energy critic for Alberta’s NDP Opposition, called for more details of Monday’s equity agreement to be immediately released.

“Albertans should be deeply concerned that Jason Kenney has made them part-owners of one of the most notorious Conservative boondoggles in Alberta history,” Ganley said in a release.

Advertisement

You are viewing an Accelerated Mobile Webpage.

View Original Article