Biden administration passes up chance to block Enbridge Line 3 oil pipeline

November 12, 2020, Superior, WI, USA: Two Minnesota regulators granted environmental permits for Enbridge's Line 3 oil pipeline across northern Minnesota, critical approvals needed for construction to begin soon on the controversial $2.6 billion project, on Thursday, Nov. 12, 2020. (Credit Image: © TNS via ZUMA Wire).

The Biden administration signaled in a court filing this week that it does not plan to cancel federal permits for Enbridge’s Energy’s Line 3 oil pipeline project, despite pleas by Native Americans and environmental groups for the president to intervene.

The U.S. Army Corps of Engineers used the filing to defend its decision in November to grant Enbridge a water permit for the project, the last major approval the Calgary, Alberta-based company needed.

READ MORE: Minnesota court affirms approval of Enbridge’s Line 3 oil pipeline

Wednesday’s filing by the Corps and its attorneys at the Department of Justice marks the first time President Joe Biden’s administration has taken a public position on Enbridge’s plan to replace its aging Line 3, which carries oil from western Canada to Enbridge’s terminal in Superior, Wisconsin, the Star Tribune of Minneapolis reported.

Environmental organizations expressed displeasure Thursday.

Story continues below advertisement

“Allowing Line 3 to move forward is, at best, inconsistent with the bold promises on climate and environmental justice President Biden campaigned and was elected on,” Michael Brune, executive director of the Sierra Club, said in a statement.

READ MORE: Protesters maintain blockade at Line 3 site in Minnesota 

But Enbridge said in a statement that the Corps’ filing “is an expected next step in the court appeal process,” and that it laid out the federal agency’s “very thorough review” of Line 3’s federal permits.

Two Ojibwe bands and three environmental groups sued the Corps in federal court late last year. They claimed the Corps did not properly evaluate the pipeline’s impact on climate change, and that the agency should have conducted its own, full environmental impact study on the pipeline instead of relying on the state’s. Their lawsuit also alleges that the Corps failed to fully consider treaty rights. The pipeline crosses lands where several tribes claim treaty rights to hunt, gather and fish.

The Corps asked for the case to be dismissed, saying the agency met all requirements under federal environmental law. The permit allows Enbridge to drill beneath certain rivers during construction and discharge dredged material.

READ MORE: June a critical month for Enbridge’s Line 3 oil pipeline

The Minnesota segment of the pipeline is more than 60 per cent complete. The Wisconsin and Canadian sections are already carrying oil. Protests along the route in Minnesota have ramped up significantly over the past few weeks.

Story continues below advertisement

Since Biden took office in January, opponents of Line 3 have repeatedly called for him to stop the project. The most practical legal way for him to do that would be by revoking Line 3’s Army Corps permit, or by ordering that the permit to be redone.

“Today’s decision is the Biden administration on autopilot, defending a Trump water permit for a massive tar sands pipeline that is actually indefensible,” said Andy Pearson, an organizer with MN350, a climate change group.