Advertisement

Minnesota regulators give key approvals for Line 3 pipeline

Click to play video: 'Enbridge Line 3 replacement pipeline delayed'
Enbridge Line 3 replacement pipeline delayed
WATCH (March 4, 2019): Alberta has suffered yet another blow in its efforts to build a pipeline to carry crude out of the province. As Tom Vernon reports, this comes from a U.S. decision delaying Enbridge Line 3 by a year – Mar 4, 2019

Minnesota utility regulators on Monday approved a court-ordered revised environmental review for Enbridge Energy’s plan to replace its aging Line 3 crude oil pipeline across the state.

The state Public Utilities Commission voted 3-1 to approve the environmental impact statement for the $2.6-billion project, saying the new review adequately addressed the impacts of a potential spill in the Lake Superior watershed.

Commissioner Matt Schuerger disagreed with the majority, saying the updated review “doesn’t adequately represent the consequences of a spill,” the Star Tribune reported.

But commissioner Valerie Means, who was not on the board in 2018 when the commission originally approved an environmental impact statement for the project, said she believes “there has been a sufficient evaluation.”

Story continues below advertisement

Means, Chairwoman Katie Sieben and commissioner John Tuma all voted to approve the revised environmental impact statement. They also agreed, on the same 3-1 vote, to reissue a certificate of need that the disputed project needs to proceed.

The new pipeline would replace Enbridge’s Line 3, which was built in the 1960s. Enbridge, based in Calgary, Alta., says the old line needs to be replaced because it is increasingly prone to corrosion and cracking and can run at only about half its original capacity. Environmental and tribal activists have urged regulators to kill the project.

Click to play video: 'Enbridge shows off early stages of Line 3 replacement near Morden'
Enbridge shows off early stages of Line 3 replacement near Morden

The commission approved an environmental review in March 2018. But the Minnesota Court of Appeals sent the previous final version of the project’s environmental review back to the commission after finding that the massive document failed to adequately deal with the potential risks of an oil spill in the Lake Superior watershed. The state Department of Commerce then conducted additional modeling and concluded in the update that there was little chance of a spill reaching the lake.

Story continues below advertisement

READ MORE: Line 3 pipeline setback more bad news for Canadian oilfield workers: CEO of industry group

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.

Get breaking National news

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

During a public hearing Friday, environmental and tribal activists argued against the project, saying climate change has reached a crisis stage. But the project’s supporters, including union construction workers, testified it’s time to let project move forward.

Line 3 starts in Alberta and clips a corner of North Dakota before crossing northern Minnesota en route to Enbridge’s terminal in Superior, Wisconsin. Enbridge said in a filing ahead of Friday’s hearing that the record continues to show the project is needed.

Sponsored content

AdChoices