Work begins on Saturday to remove crane toppled by Dorian

The twisted remains of a building crane hang off a construction project in Halifax Nova Scotia in the wake of Dorian, Sunday, Sept. 8, 2019. Andrew Vaughan/The Canadian Press via AP

A structural engineering report has been completed and approved.

Story continues below advertisement

The twisted, yellow structure is draped over a building that was under construction in the city’s downtown.

WATCH: Video captures moment crane collapses in downtown Halifax during storm

Video posted on social media showed the dramatic collapse at the height of the heavy rain and high winds September 7th.

The daily email you need for 's top news stories.

The first work this weekend will see crews going from floor to floor to shore up the building in case it’s been compromised.

Story continues below advertisement

Posts will be put in place to ensure the building doesn’t fall in case there are any compromised support columns.

READ MORE: HRM to cover fees for recycling residential tree waste after hurricane Dorian

A drone belonging to Halifax Regional Fire and Emergency could be seen flying around the building yesterday to assist crews in their assessment.

An official says the work should take about two weeks.