There will be one more round of asphalt testing before the Red Hill Valley Parkway (RHVP) is closed for resurfacing.
The City of Hamilton says there will be rolling lane closures starting at 9:30 Tuesday morning in the left lane of the northbound, or downbound, RHVP.
The rolling closures are to allow for one more round of sample collection and testing of the current asphalt surface, and they will happen at five different locations in the left lane throughout the day on Tuesday.
Get daily National news
In a release, the city states that the data compiled “may inform ongoing litigation matters.”
READ MORE: Families of Red Hill Valley Parkway crash victims launch $250M class-action against City of Hamilton
The city also says the Commissioner overseeing a judicial inquiry into the Red Hill Valley Parkway matter “has indicated its support of the testing as it may assist the work of the judicial inquiry.”
- Heavy traffic gridlock in southwest Edmonton as construction ramp up: ‘Everyone is frustrated’
- Edmonton’s historic High and Low level bridges to be replaced: ‘Run their course’
- 3 people taken to hospital after Calgary Transit bus rollover
- Lewvan-Dewdney intersection gets green light for safety improvements
A full closure of the northbound parkway for resurfacing will begin as scheduled Tuesday night at 9 p.m., between the LINC and the QEW.
That closure is scheduled to last about three weeks and a resurfacing of the southbound lanes of the RHVP will follow in mid-June.
Other safety improvements will also be made during the closures including 10 kilometres of steel guide rails with reflectors, bright durable lane markings, and rumble strips.