March 13, 2019 4:23 pm

Natural Resources Minister Sohi says Indigenous consultations on TMX proceeding on schedule

Natural Resources Minister Amarjeet Sohi speaks during a news conference in Ottawa on October 3, 2018. Natural Resources Minister Amarjeet Sohi says consultations with Indigenous groups about the stalled Trans Mountain pipeline expansion are going well and he expects to wrap up the process by May.

THE CANADIAN PRESS/Adrian Wyld
A A

Natural Resources Minister Amarjeet Sohi says consultations with Indigenous groups about the stalled Trans Mountain pipeline expansion are progressing well and he still expects to wrap up the court-ordered process by May.

On a conference call from Houston, where he’s attending the CERAWeek energy conference, Sohi told reporters his department has now met with more than 100 of the 117 Indigenous communities expected to be impacted by the project.

Story continues below

READ MORE: Feds in ‘very strong position’ to wrap Indigenous Trans Mountain consultations within 90 days: Sohi

The Federal Appeal Court last summer overturned approval of the project to triple oil shipments from Edmonton to the West Coast, ruling that the NEB had not properly considered its impact on marine life nor had Ottawa meaningfully consulted with Indigenous groups.

Last month, the National Energy Board found that the pipeline is still in the public interest despite the risk that an increase in tanker traffic could adversely affect southern resident killer whales, hurt related Indigenous culture and increase greenhouse gas emissions.

READ MORE: Alberta Premier Rachel Notley calls for major amendments to Bill C-69 in Senate address

It added 16 new recommendations for federal government action in addition to the 156 conditions in its initial approval in 2016.

Sohi says the recommendations, which the NEB said are not within its power to order, are already being studied by his department and will be considered in the government’s decision on TMX when consultations are complete.

READ MORE: Feds announce initial step to help large emitters cut greenhouse gasses

“The NEB report informs our ongoing consultations and those recommendations will be discussed once the cabinet is ready to make the final decision,” he said.

Cabinet is under immense pressure to decide the fate of the pipeline before the federal election in the fall.

There is also pressure to get the expansion built because Ottawa bought the existing pipeline from Kinder Morgan for $4.5 billion last August, after political opposition to the expansion left the company’s shareholders reluctant to proceed.

© 2019 The Canadian Press