Survey showing support for nuke waste bunker near Lake Huron ‘misleading’

This Nov. 1, 2013 photo shows rows of chambers holding intermediate-level radioactive waste in shallow pits at the Bruce Power nuclear complex near Kincardine, Ontario.
This Nov. 1, 2013 photo shows rows of chambers holding intermediate-level radioactive waste in shallow pits at the Bruce Power nuclear complex near Kincardine, Ontario. THE CANADIAN PRESS/AP Photo-John Flesher

TORONTO – A public opinion survey used to bolster claims of widespread support for a proposed nuclear waste bunker near Lake Huron was misleading and actually found little backing for the project, critics say.

While Ontario Power Generation stands by the poll of 805 people, critics insist an analysis shows the utility distorted its findings in submissions to the federal government.

Among other things, poll questions provided false or misleading assumptions designed to skew the response in favour of the deep geologic repository, they said.

Far from showing that a majority of people in Ontario support the repository, the poll actually shows most people oppose it, said Rod McLeod, with the group SOS Great Lakes.

READ MORE: Moving planned nuclear-waste bunker on Lake Huron would cost $2.4B: OPG report

“It is clear that OPG misrepresented the findings to the government, to the media and the public,” said McLeod, a retired lawyer and former deputy minister of the environment. “They excel at alternative facts.”

Story continues below advertisement

McLeod called it astounding how far OPG appeared willing to go to misrepresent data to the federal government, which has yet to decide if the project should proceed over the objections of hundreds of communities on both sides of the Canada-U.S. border.

Breaking news from Canada and around the world sent to your email, as it happens.

Kevin Powers, a spokesman for OPG, stood by a survey he said was done by one of the top polling firms in the country. Its methodology was scientifically sound and the questions were ordered to prevent bias, he said.

Powers also said reference to its results amounted to just a “single paragraph” in a 700-page report to the government which was among 15,000 pages of evidence showing the project has been proven scientifically safe.

READ MORE: Decision on storing Ontario nuclear waste delayed again for more study

“The survey was intended to give us a clear understanding of what people thought about the (repository) not give us results that we wanted to hear,” Powers said.

“We feel that geology, physics, geoscience and engineering – not opinion research – should guide decision making on this project.”

In a recent submission to the federal minister of the environment, OPG cites the Gandalf Group survey as showing barely more than half of people in Ontario were even aware of the project. The utility then states that 60 per cent of those who had heard about it – based on “their initial understanding” of the project – were supportive.

Story continues below advertisement

READ MORE: Federal government pushes back decision on proposed nuclear-waste bunker near Lake Huron

Robin Palin, a public-relations consultant in Montreal who analyzed the survey, said the upshot of the poll is that it found 33 per cent support among respondents for a repository somewhere in the province.

“There are no other numbers in the entire poll that can be considered statistically-valid representations of Ontario public opinion,” Palin said.

In addition, he said, survey participants were fed unsupportable statements favouring the project. One example was a statement that “experts from around the world, including the U.S. Environmental Protection Agency, agree that this deep geologic repository will protect the environment from nuclear waste.”

At best, the critics say, some international experts support the project but others believe such it would be unsafe, and that the American environmental agency has not actually expressed an opinion.

The Canadian Environmental Assessment Agency is currently examining the latest OPG submissions on whether there are better alternatives to digging the bunker in bedrock about 1.2 kilometres from Lake Huron.

The project, currently estimated to cost $2.4 billion, would see a bunker built at the Bruce nuclear power plant near Kincardine, Ont. Hundreds of thousands of cubic metres of low and intermediate radioactive waste – now stored at the site above ground – would be buried 680 metres deep.