Transportation Safety Board says loose screws were to blame for January derailment

The Transportation Safety Board of Canada (TSB) has found the Canadian National (CN) train derailment from January 21, 2012 near Fabyan, Alberta was caused by loose and broken rail screws.

The TSB released its investigation report into the derailment Thursday morning.

Its findings show the train was heading west on the Wainwright subdivision towards Edmonton. The TSB says when the train crossed the Fabyan Bridge, the outside rail in the curve at the east end of the bridge rolled over, causing 31 cars to derail.

There were no dangerous goods involved. No one was injured in the derailment.

Get daily Canada news delivered to your inbox so you'll never miss the day's top stories.

Get daily National news

Get daily Canada news delivered to your inbox so you'll never miss the day's top stories.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

Back in January, when the 31 grain cars derailed, some people in the area were concerned about the possible environmental impact, since 17 of those cars fell off the trestle bridge and into the river valley. However, CN assured the public there was no negative impact on the environment.

Story continues below advertisement

In late January, there were a total of three CN derailments in the span of one week; the Wainwright incident, one near Hay Lakes and another between Hinton and Grande Cache.

At the time, the TSB said it would investigate two of those derailments.

“They’ll take a look at the accident and determine if there’s anything to be gained by doing an investigation that will fulfill our mandate to advance transportation safety in Canada,” said John Cottreau with the board.

The TSB investigation found that a number of lag screws, meant to hold the track in place in the curved section, progressively failed. The report found there were not enough remaining screws to secure the track as the train continued around the curve.

The board says a number of track inspections took place in the days before the derailment. However, those inspections did not detect that the curve was under stress, and action was not taken to adequately secure the curve.

Following the derailment, TSB says CN improved its protocols for inspecting curves, turnouts and bridge decks with screw spikes. The company is also requiring stronger rail fastener systems in some curves.
 