TOKYO – A court issued an unprecedented order Wednesday for a nuclear reactor in western Japan to stop operating and ordered a second one to stay offline.

The Otsu District Court that issued the injunction said the emergency response plans and equipment designs at the two reactors have not been sufficiently upgraded after the 2011 Fukushima nuclear disaster.

The order requires Kansai Electric Power Co. to shut down the No. 3 reactor and keep the No. 4 offline at the Takahama plant in Fukui prefecture, home to about a dozen reactors.

The two reactors restarted this year after a high court in December reversed an earlier injunction by another court. The No. 3 reactor, which uses a riskier plutonium-based MOX fuel, resumed operation in late January, while the No. 4 reactor had to be shut down late last month after operating just three days because of a series of technical problems.

Story continues below advertisement

READ MORE: Containing Fukushima’s radioactive water may be 9-year fight

Kansai Electric said it will abide by the decision and start the shutdown procedures for No. 3 reactor Thursday morning. The utility, meanwhile, said the decision was “disappointing” and planned to appeal.

The decision reflects Japan’s divisive views on nuclear safety and leaves only two of the country’s 43 reactors in operation.

Judge Yoshihiko Yamamoto said the operator has not fully explained how exactly it has upgraded safety features at the two Takahama reactors under the post-Fukushima safety standards. The utility has not fully explained its design philosophy, its measures to mitigate power loss and how to carry out evacuation plans in case of a severe accident and a massive tsunami, he said in the ruling.

The decision also shakes the credibility of the stricter safety requirements made after Fukushima. Wednesday’s ruling supported concerns by residents and experts that the stricter standards still do not require utilities to have adequate evacuation plans before applying to restart reactors.

READ MORE: Melted nuclear fuel from Fukushima disaster is missing, company says

Nuclear Regulation Authority Chairman Shunichi Tanaka declined to comment on the ruling, but defended the new requirements, which incorporated lessons learned from the Fukushima disaster.

Chief Cabinet Secretary Yoshihide Suga told reporters that the government stands by the regulators’ standards and that plans to restart Takahama and other reactors deemed safe are unchanged.

Story continues below advertisement

Prime Minister Shinzo Abe’s government wants to restart as many reactors as possible. It says nuclear energy should remain a key power source for Japan, which has few natural resources to fuel its economy.

READ MORE: 3 ex-execs of utility charged in Fukushima disaster

Lawyers for the plaintiffs welcomed the ruling as “fair, calm and wise,” raising questions over the utility’s safety culture and the regulators’ safety standards.