Advertisement

1 month of southwest Anthony Henday Drive bridge closures begins Friday

Click to play video: 'Southwest Anthony Henday Drive bridge construction in the final stretch'
Southwest Anthony Henday Drive bridge construction in the final stretch
WATCH: The southwest Anthony Henday Drive bridges over the North Saskatchewan River as seen from the Global 1 news helicopter on Friday, June 23, 2023 – Jun 23, 2023

Edmonton drivers, the end is finally in sight — but first, there will be even more major traffic backlogs on the southwest leg of Anthony Henday Drive.

For three years, drivers have endured extensive construction on the busy stretch of the city’s ring road and for the next month, it will get even worse — but Alberta Transportation said that will be the last major disruption before the expansion project is, for the most part, complete.

Construction has been ongoing since 2020 to widen each bridge deck over the North Saskatchewan River from two to three lanes of traffic, as part of the overall much-needed widening of the southwest leg.

Click to play video: 'Construction scheduled to widen Anthony Henday in southwest Edmonton'
Construction scheduled to widen Anthony Henday in southwest Edmonton

Several times in the past year, the province — which is responsible for the freeway — and construction contractor Carmacks have closed one deck at a time on the weekend.

Story continues below advertisement

Starting Friday, however, there will be two-week-long closures on either side of the road.

The province said the two-week closures are for getting the final support structures in place, pouring the new bridge decks and final paving.

Click to play video: 'Anthony Henday Drive bridge construction causing major traffic headaches'
Anthony Henday Drive bridge construction causing major traffic headaches

As of 10 p.m. Friday, the westbound bridge will close for two weeks. Immediately after, starting July 7, Alberta Transportation said the eastbound bridge will close for an additional two weeks.

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.

Get daily National news

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

That means all traffic will be rerouted to the opposite bridge — flowing one lane in each direction — and the speed limit will be reduced to 60 km/h.

1 month of southwest Anthony Henday Drive bridge closures begins Friday - image

That bottleneck is expected to cause significant delays on the freeway and drivers in the city are advised to take other routes such as Whitemud Drive.

Story continues below advertisement

Oversized and overweight trucker loads will not be permitted to use the Henday during the weekend closures, the province said.

Click to play video: '1 month of southwest Anthony Henday Drive bridge closures begins Friday'
1 month of southwest Anthony Henday Drive bridge closures begins Friday

Those looking to bypass the city can also take Highway 60 through Devon, although similar bridge deck rehabilitation work has been ongoing there since last summer as well, and one of those bridges is also flowing in one lane of traffic in each direction.

This past week, crews have been seen removing fencing and moving concrete barricades in anticipation of construction work.

Alberta Transportation said after that month of closures, the bridge work should be complete.

The southwest leg of Anthony Henday Drive near the bridges over the North Saskatchewan River on Friday, June 23, 2023. Global News

The project is a year behind schedule but the province said the entire southwest Henday widening project — from Gateway Boulevard to Whitemud Drive — is on track to be complete by September.

Story continues below advertisement

The Henday was originally designed to meet traffic capacity requirements through 2020 with a plan to accommodate up to 40,000 vehicles per day.

The entire ring road took 26 years to build, and as it grew, so too did the surrounding neighbourhoods.

That initial capacity in southwest Edmonton was surpassed in 2009 and by 2020, traffic volumes averaged 80,000 vehicles per day, according to Carmacks.

Work to expand an 18-kilometre stretch between Calgary Trail and Whitemud Drive began in 2020.

Adding an extra lane in each direction is expected to accommodate up to 120,000 vehicles per day.

Sponsored content

AdChoices