Supreme Court sides with Hydro-Québec in Churchill Falls dispute

Click to play video: 'Why Quebec gets most out of Churchill Falls power plant'
Why Quebec gets most out of Churchill Falls power plant
WATCH ABOVE: Why Quebec gets most out of Churchill Falls power plant – Nov 2, 2018

The Supreme Court of Canada says there is no legal obligation to reopen the 1969 Churchill Falls energy deal that has been highly profitable for Hydro-Québec but much less so for Newfoundland and Labrador.

In a 7-1 ruling Friday, the high court says it cannot force the parties to renegotiate the contract even though the arrangement has turned out to be unexpectedly lucrative for the Quebec utility.

Under the deal signed decades ago, Hydro-Québec agreed to buy almost all the energy generated by the power plant on the Churchill River in Labrador.

WATCH: The Supreme Court of Canada has put a rest to the ongoing legal battle between Quebec and Newfoundland and Labrador. As Global’s Raquel Fletcher reports, the court says the two provinces do not need to renegotiate the 1969 Churchill Falls energy deal.

Click to play video: 'Supreme Court of Canada rules in favour of Hydro-Québec over Churchill Falls energy deal'
Supreme Court of Canada rules in favour of Hydro-Québec over Churchill Falls energy deal

READ MORE: Supreme Court to rule on Quebec-N.L. feud over Churchill Falls hydro riches

The contract, covering 65 years, set a fixed price for the energy that would decrease over time. It has earned more than $27.5 billion for Hydro-Québec to date and about $2 billion for Newfoundland and Labrador.

Story continues below advertisement

Churchill Falls (Labrador) Corporation Ltd. went to Quebec Superior Court in 2010, arguing unsuccessfully that the sizable profits from electricity were unforeseen in 1969 and that Hydro-Québec had a duty to renegotiate the contract.

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.

Get breaking National news

For news impacting Canada and around the world, sign up for breaking news alerts delivered directly to you when they happen.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

An appeal court affirmed the ruling, but the Supreme Court agreed to hear the corporation’s case.

READ MORE: Supreme Court to hear bid to reopen Churchill Falls hydro station

In its ruling, the high court says there is no legal basis in Quebec civil law for the claim advanced by the corporation, known as CFLCo, part of Newfoundland and Labrador Hydro.

A majority of the Supreme Court says CFLCo was seeking to undo certain aspects of the contract while keeping the ones that suit it. In effect, it was asking Hydro-Quebec to give up the benefits it obtained in exchange for the sacrifices it made to get the massive project up and running — a situation from which CFLCo has been benefiting since 1969 and continues to benefit today.

“In the final analysis, CFLCo has not provided any compelling factual or legal basis for the courts to reshape the contractual relationship it has had with Hydro-Québec for the last 50 years,” the court says.

The landmark decision could have a profound influence on relations between Quebec and Newfoundland and Labrador, given long-standing tensions over the historic energy deal. The project, championed in the early days by then-Newfoundland premier Joey Smallwood, has been a persistent sore point.

Story continues below advertisement

READ MORE: Newfoundland to appeal Churchill Falls ruling

The Churchill River in Labrador drops more than 300 metres over a stretch of less than 32 kilometres, making the falls one of the world’s most significant sources of hydroelectric power. A massive underground power station, carved out of solid granite, produces over 34 billion kilowatt-hours of energy annually.

In its submission to the Supreme Court, CFLCo said the energy market and regulatory landscape in 1969 were vastly different than they are today: energy was a public good with no real market value, and exports were simply a means of disposing of surpluses and required legislative authorization. Hydro-Québec was a public service provider, required by law to sell electricity to Quebec consumers at a low price.

Over the decades, everything has changed, CFLCo argued. Energy has become a supply-and-demand commodity with lucrative export markets.

In turn, Hydro-Québec’s mandate evolved and the utility has made billions of dollars selling power to Quebecers and billions more exporting to previously non-existent markets at 20 to 40 times the contract price, CFLCo told the court. Meantime, the corporation remains stuck in 1969, with a fixed, declining electricity price.

‘This is unwarranted under the civil law of Quebec’

Hydro-Québec argued that under the contract it assumed the risk associated with any fluctuations in the market value of energy, which made financing the Churchill Falls project possible. In return, Hydro-Quebec had assurance that the price set in the contract would provide the utility, for the full term, with stable supply and protection against inflation.

Story continues below advertisement

In reality, CFLCo was seeking a new contractual balance bearing no relation to the original one struck by the parties — redress that falls outside the role and function of the courts, Hydro-Québec said.

The Supreme Court agreed, concluding the significant changes in the electricity market over the years do not justify disregarding the contract’s terms.

READ MORE: Muskrat Falls public inquiry over cost overruns begins

Hydro-Québec spokesman Cendrix Bouchard welcomed the ruling, saying it confirms the utility has acted in good faith while negotiating and administering the contract. Hydro-Québec hopes the conclusion of the lengthy legal process means “the beginning of a new chapter” for the partners, he added.

Though the project began generating power in the early 1970s, the contract formally took effect in 1976 with a 40-year term and an automatic 25-year extension — meaning it expires in September 2041.

In its ruling, the Supreme Court notes the terms of the contract will see CFLCo begin operating a plant worth more than $20 billion for its own benefit.

The lone dissenting judge was Malcolm Rowe of Newfoundland and Labrador, who says Hydro-Québec has disavowed the relationship of trust and co-operation created by the contract — turning it into one of “unilateral exploitation.”

“This is unwarranted under the civil law of Quebec.”