Building the new Champlain Bridge: A race against time

Click to play video: 'Will the new Champlain Bridge be finished on time?'
Will the new Champlain Bridge be finished on time?
WATCH: After a week-long crane operator strike, some are questioning if the Champlain Bridge will be completed by this winter. As Global's Tim Sargeant reports, missing the December deadline would mean stiff fines and millions of dollars to keep the old bridge open longer than planned – Jun 27, 2018

Time is not on the side of workers and officials rushing to finish the new Champlain Bridge on time.

READ MORE: Groups behind Montreal’s new Champlain Bridge say project will be done on time

While the deadline of Dec. 21 is still about six months away, the recent strike by crane operators could put the delivery date in jeopardy.

READ MORE: New Champlain Bridge celebrates one year of construction

Officials heading the consortium, led by SNC-Lavalin, insist they’re still striving to meet the deadline, but admit they do need to reassess.

Story continues below advertisement

Crane operators walked off the job June 14, not returning until a tribunal ordered them back to work from their “illegal” one week strike.

Get expert insights, Q&A on markets, housing, inflation, and personal finance information delivered to you every Saturday.

Get weekly money news

Get expert insights, Q&A on markets, housing, inflation, and personal finance information delivered to you every Saturday.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

READ MORE: New Champlain Bridge now expected to open December 21

WATCH BELOW: When will the new Champlain Bridge open?

Click to play video: 'When will the new Champlain Bridge open?'
When will the new Champlain Bridge open?

Dozens of crane operators are helping to build the $4.2 billion span that stretches 3.4 km across the Saint Laurence River.

READ MORE: Montreal’s new Champlain Bridge on schedule

It is a critical link for daily users to-and-from the South Shore, as well as tourists and commercial trade.

Story continues below advertisement

About 160,000 vehicles a day use the bridge and more than $20 billion worth of commercial trade crosses every year, most of it between Canada and the U.S.

READ MORE: 2,000 defects found on Montreal’s new Champlain Bridge

Officials for the existing Champlain Bridge, which opened in 1962, say they have set aside $10 million for maintenance and repair costs in order to keep it open until next June — in the event the new structure isn’t finished.

READ MORE: Workers on overdrive to finish Montreal’s new Champlain Bridge

The consortium will face a fine of $100,000/day for the first seven days the bridge is late, and $400,000/day after the first week.