Road work begins to complete rocky Beaconsfield bike path

WATCH: After an uneven paving job on Elm Avenue left Beaconsfield residents confused and infuriated, officials say workers are now making sure the job is completed properly. Global's Felicia Parrillo reports – Aug 4, 2017

It’s been a long and bumpy road for the bike path on Elm Avenue in Beaconsfield.

Story continues below advertisement

After almost a year of work, Elm Avenue was reopened to motorists Monday, but the road was left unfinished and uneven.

READ MORE: Unfinished business on Beaconsfield bike path?

After Global News’ story aired, the City of Beaconsfield explained Jeskar Construction, the company that holds the contract, was given 24 hours to fix the street.

“Jeskar was suppose to certainly leave the street in drivable condition,” said Beaconsfield Mayor Georges Bourelle.

“Of course, we had told the agglomeration we were going to be re-surfacing the area, but that’s not a reason to leave the street in that condition.”

Financial news and insights delivered to your email every Saturday.

Construction began in September and was slated to last three months.

READ MORE: Beaconsfield bike path project to be completed in 3 months

The contract was awarded by the City of Montreal for $1.5 million.

Story continues below advertisement

On Friday, Roxboro Construction, hired by Beaconsfield, were out to pave the road.

Though it seems things are now back on track, Bourelle says these issues may have been avoided if Beaconsfield was able to manage the project, instead of Montreal.

READ MORE: Beaconsfield mayor wants contract-awarding process revisited after bike path construction delays

“We are close to the scene, we can react quickly, we can supervise the work much more quickly than say, somebody from a remote area of Montreal can do,” he said.

People who live in the area insist they don’t care whose responsibility it is.

“As long as it’s done and as long as we don’t have to pay extra taxes,” said Beaconsfield resident Elaine Sanders.

READ MORE: Beaconsfield residents not happy about bike lane construction

Residents say they’re looking forward for construction to finally come to an end.

Story continues below advertisement

“It’s always longer than we’d want it to be, but at the same time, we want it to be of good quality so it lasts, ” said Patrice Tremblay.

The ribbon cutting is scheduled to take place Aug. 29.