LUNENBURG, N.S. – Nova Scotia’s historic schooner Bluenose II is expected to return to the water in about two months, according to an email sent by the ship’s captain.
A tentative plan released by Capt. Wayne Walters in an email sent to the Lunenburg board of trade, and obtained by CKBW radio, indicates the vessel could be back in the water in July, though no firm date has been announced yet.
“The tentative plan at this time is to put Bluenose II in the water in early July. A firm date will be circulated when it becomes available,” says the email from Walters.
Get breaking National news
CKBW contacted Walters, but he declined to comment on the email.
The email from Walters also says the project is expected to be completed in late September.
He says there is no public sailing scheduled for this year, but that is expected next summer.
However, a spokesman for the province’s Department of Communities, Culture and Heritage said in an email that no schedule for the vessel’s refit has been released by the province.
“Further, no date for her relaunch has been scheduled by the province,” said Michael Noon, the department’s director of communications.
He said in an interview that the dates remain undecided.
“All I can say to you is that there is no date set yet,” he said.
The boat is undergoing a $15.9-million refit in Lunenburg that includes a new hull, frame and planking.
The original Bluenose was built in 1921.
Bluenose II was built in 1963 and transferred to the province in 1971.