St. Paul’s Hospital gets $17.2 million in funding for electrical upgrades

Ward 10C at St. Paul's Hospital first opened in 1997 when the HIV/AIDS epidemic was at its peak. During that time, nearly one person was dying from AIDS in Vancouver every day.
Ward 10C at St. Paul's Hospital first opened in 1997 when the HIV/AIDS epidemic was at its peak. During that time, nearly one person was dying from AIDS in Vancouver every day.

VANCOUVER — The province provided $17.2 million to St. Paul’s Hospital Thursday to replace aging generators and electrical components, as well as elevators.

The funding announcement by B.C. Health Minister Mike de Jong comes seven months after the hospital suffered a 10-second complete power failure that plunged the hospital into darkness.

At the time, hospital officials said the power failure was a “wake-up” call, and said it was lucky it happened at night when no surgeries were underway.

Some portions of St. Paul’s Hospital are 100 years old.

Get breaking Canada news delivered to your inbox as it happens so you won't miss a trending story.

Get breaking National news

Get breaking Canada news delivered to your inbox as it happens so you won't miss a trending story.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

Following the power outage last February, the province provided $1 million in emergency funding.

Another $12.5 million was provided Thursday to replace transformers, automatic transfer switches and switch gears, as well as generators.

Story continues below advertisement

The hospital will also receive $4.7 million to upgrade its elevators. The 20 to 40-year-old elevators have experienced shut downs and slow service.

“The elevator and electrical upgrades are a crucial step in ensuring continued excellence and innovation in care delivery, and are foundational to [Providence Health Care’s] planning for the hospital’s redevelopment,” Providence president and CEO Dianne Doyle said in a news release.

Providence Health Care and Vancouver Coastal Health have submitted a plan for the renewal of the hospital, which is being reviewed by the province.

Following the power outage, hospital officials said they had been working with the provincial government to try to secure $610 million in capital funding for new buildings.

 