Winnipeg sewage treatment plant upgrades to cost $80 million more than expected

The City of Winnipeg will be paying much more than expected for upgrades to its sewage plants. File / Global News

Massive upgrades planned for Winnipeg’s sewage treatment plants will be coming in at a much bigger price tag than originally expected — to the tune of more than $80 million — according to details from the city’s finance committee meeting Tuesday.

Story continues below advertisement

Upgrades to the South End Sewage Treatment Plant have fallen behind schedule, the committee was told, adding an estimated $16.5 million to the project.

An additional $65 million is attached to the North End Sewage Plant, a price the city says is due in part to building a new headworks facility at the plant.

The daily email you need for Winnipeg's top news stories.

Increased costs and delays for both projects are also related to the impact the COVID-19 pandemic has had on contractors bidding for the work.

The total new price tag for both projects comes in at $80.5 million over budget.