Round-the-clock roadwork pledges a pipe dream, says Manitoba construction group

WATCH: The Manitoba Heavy Construction Association says 24/7 construction will come at a cost, and ones who will pay the most are the people living in homes nearby – Oct 5, 2018

Despite the promise by several candidates to look at 24/7 road construction in the City of Winnipeg, the president of the local construction association says it’s just not possible here.

Story continues below advertisement

“Well, 24/7 is something that has been discussed for a quite number of years in the City of Winnipeg and it hasn’t been used, because quite frankly it can’t in this market,” said Chris Lorenc of the Manitoba Heavy Construction Association.

Lorenc said the closeness of residential homes to streets means the noise carries and disrupts neighbourhoods. Doing that around the clock would prompt nothing but complaints, he said.

“When industry was building the Waverley extension, we were getting complaints from residents well beyond a kilometre away, to the police department that the construction noise was traveling.”

WATCH: Lengthy construction projects caused by City of Winnipeg cost-control: MHCA

Winnipeg mayor Brian Bowman pledged Friday to commit to an industry working group tasked with looking into 24/7 construction, improving communication between residents and businesses and looking at early procurement to local roads should he be re-elected Oct. 24.

Story continues below advertisement

Candidate Jenny Motkaluk called the pledge an “imitation.”

The daily email you need for Winnipeg's top news stories.

“I would like to thank Brian Bowman for … reiterating the great ideas that I and other candidates have already tabled on smarter procurement and infrastructure planning,” she said in a statement sent to media.

Trying 24/7 construction would be more expensive as well, said Lorenc, and has its own challenges.

“We have enough people, but how much do you want to pay for your construction … we can’t source inspectors in the middle of the night. There are safety issues that apply that don’t apply during daylight hours.”

WATCH: MHCA says there are better ways to go than 24/7 construction

Lorenc said there are other ways to speed up construction, including using concrete that cures faster and shutting down streets completely to shorten the construction period.

Story continues below advertisement

In 2018, the city saw record-breaking road construction in terms of money spent. A map of road construction projects happening in the city online.

This year’s budget included $116 million for improvements to local and regional streets, back lanes and sidewalks.

By the time it’s all said and done, the city said it expects to have completed 150 lane kilometres of improvements.

In 2017 the city budgeted $105 million in road repairs.