Quebec agency releases Lac-Megantic report

In this July 6, 2013, file photo, smoke rises from railway cars that were carrying crude oil after derailing in downtown Lac Megantic, Que. Quebec's environmental review agency says the majority of Lac-Megantic residents appear to favour keeping the railway track in the town, Tuesday, August 1, 2017.
In this July 6, 2013, file photo, smoke rises from railway cars that were carrying crude oil after derailing in downtown Lac Megantic, Que. Paul Chiasson / The Canadian Press

The population of Lac-Megantic and its neighbouring towns are heavily divided on what to do with the railway that runs through the heart of the town, Quebec’s environmental review agency said Monday.

The agency, known as the BAPE, favoured one of three possible rail bypass options on the table in a 77-page report.

But the BAPE also said leaving the current rail track untouched merits a fuller treatment — a position Lac-Megantic has excluded.

READ MORE: Lac-Mégantic marks 4th anniversary of rail tragedy

The debate over a rail bypass has raged since a train carrying crude oil derailed and exploded in July 2013, killing 47 people and wiping out much of Lac-Megantic’s downtown core.

Pierre Mercier, Lac-Megantic’s deputy mayor, said in an interview the status quo is being excluded by the town because “it is so obvious” it isn’t an option.

Story continues below advertisement

“We need a bypass, it is the only option,” Mercier said. “Maybe we’re being rapped on the knuckles a bit (by the BAPE), but for us it is obvious that we need a bypass.”

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.

Get daily National news

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

READ MORE: Bilingual Lac-Mégantic criminal negligence trial to be held in Sherbrooke

The city said it was pleased the agency came out in favour of one of the bypass options.

The agency called the 11.7-kilometre option, which would cost an estimated $115 million and include the dismantling of the current track, the best option from an environmental, social and economic standpoint and should be considered.

It made its recommendations after hearing from some residents and participants in public consultation hearings between May and July.

READ MORE: Lac-Mégantic residents call on Trudeau to move forward on rail bypass

Some citizens believe the bypass will do nothing except move the problem elsewhere while others are firm the bypass solution is essential.

Of those who participated, the agency noted that 59 Lac-Megantic residents were in favour of the status quo, while 43 favoured a bypass. In nearby Frontenac, 30 opted for the status quo and four preferred a bypass.

The BAPE concluded a lot of work still needs to be done before finding an adequate solution for the municipality.

Story continues below advertisement

The agency says residents need to be better informed about the possible consequences of keeping the current railway track as is.

“None of the rail bypass proposals seem to adequately and satisfactorily to their expectations,” the agency noted.