Advertisement

NDG road work finished ahead of schedule and under budget

Road work in Cote-des-Neiges-NDG has not only finished ahead of schedule, but also under budget, Thursday, October 6, 2016. Billy Shields/Global News

Road work in Côte-des-Neiges—Notre-Dame-de-Grâce, Que. has not only finished ahead of schedule, but also under budget.

The borough invested $17 million in the project last spring, which included more than 24 kilometres of road repairs and 18 kilometres of sidewalk repairs.

Breaking news from Canada and around the world sent to your email, as it happens.

READ MORE: About 10% of NDG roads set to get makeover this year

The remaining funds will be put towards more road work as the borough is seeing an unprecedented amount of road repairs since its creation in 2002.

Contracts for the road work were given out in May with the project originally slated for completion by November.

Sponsored content

AdChoices