Dorval overpass stalled by legal dispute

Dorval overpass stalled by legal dispute - image

Work to complete an overpass in Dorval hasn’t been touched for months.

A legal dispute between Transport Quebec and the Fairfield Marriot hotel has delayed completing the Dorval interchange.

The new structure linking Highway 20, the city of Dorval and the airport won’t be finished until 2017 – four years later than planned.

The project is also now expected to cost $350 million – which is $125 million more than the original budget.