Another setback for Ottawa LRT has north-south expansion line delayed to spring 2024

OC Transpo Light Rail Transit trains are shown n Ottawa on Monday, Sept. 25, 2023. Ottawa's light-rail transit will not open its north-south expansion line until at least April 2024. THE CANADIAN PRESS/Sean Kilpatrick

Ottawa’s light-rail transit will not open its expanded north-south line until at least April 2024, a 20-month delay to the expected delivery date in the original contract.

The last update from the city’s transit services in August had estimated the line could be opened as soon as November.

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.

Get daily National news

Get the day's top news, political, economic, and current affairs headlines, delivered to your inbox once a day.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

But OC Transpo head Renée Amilcar says that in the name of caution, the transit agency is delaying a public opening, though it is seeking a handover from contractors as soon as possible.

She says the decision means there will be more time to test the system and ensure proper training.

The extended Trillium Line will run south from Bayview Station, which is part of the city’s east-west transit line, past the Ottawa International Airport to Limebank Station near the Riverside South neighbourhood.