Menu

Topics

Connect

Comments

Want to discuss? Please read our Commenting Policy first.

New power transmission towers connect Muskrat Falls, mainland Nova Scotia

Trevor Tobin, left, and Sandy Goodyear work in the Control Room at the Lower Churchill Soldiers Pond site, 40 minutes outside of St. John's on Wednesday, June 27, 2018. Paul Daly/The Canadian Press

Nova Scotia Power says it has completed installation of six new transmission towers that will carry electricity from Labrador’s Muskrat Falls hydroelectric megaproject to mainland Nova Scotia.

Story continues below advertisement

The $20 million towers span the Strait of Canso from Cape Breton and connect to the Maritime Link system that will allow the flow of electricity from Newfoundland.

READ MORE: Power link between Labrador and Newfoundland to be ‘energized’ for first time

The towers support six high voltage power lines the utility says will also act as a backup connection between the mainland and Cape Breton in the event of an outage.

Senior project engineer Tom Flewwelling says the towers are the tallest in Atlantic Canada, adding that it took a “careful combination of personnel, cranes and helicopters to get the job done.”

The $1.6 billion Maritime Link subsea cable was laid last year and first tested in December.

WATCH: Ottawa won’t be ‘heavy-handed’ in Muskrat Falls hydro project dispute

Meanwhile, Nalcor Energy’s Muskrat Falls project has seen construction delays which have nearly doubled the estimated cost to $12.7 billion.

Story continues below advertisement

Full power is not expected from the project until 2020, about two years behind schedule.

Advertisement

You are viewing an Accelerated Mobile Webpage.

View Original Article