Mercier Bridge lane closure to last 8 weeks

WATCH ABOVE: A decade after it was first announced, work on the federal portion of the Mercier Bridge began overnight on Friday June 24 – Jun 25, 2016

MONTREAL – A blitz to replace the Mercier Bridge deck has begun.

Story continues below advertisement

For the next eight weeks the bridge connecting Kahnawake and the borough of Lasalle will be reduced to one lane in both directions.

READ MORE: Major work planned for 3 of Montreal’s bridges in 2016

The daily email you need for 's top news stories.
Get the day's top stories from  and surrounding communities, delivered to your inbox once a day.

Get daily news

Get the day's top stories from and surrounding communities, delivered to your inbox once a day.
By providing your email address, you have read and agree to Global News' Terms and Conditions and Privacy Policy.

Construction will be completed in two phases, the first will close the access ramp from Chateauguay to Montreal.

The second will add the closure of the access ramp from La Prairie towards Montreal.

A speed limit of 50 kilometres per hour has been imposed, and trucks will not be allowed on the bridge during rush hour.

READ MORE: Construction to affect traffic around Mont-Royal park and McGill University

The federal authority, The Jacques Cartier and Champlain Bridges Incorporated, recommends using public transportation or carpooling.

An alternate route to reach Chateauguay and Kahnawake by car is the Champlain Bridge using the Highway 132 West access ramp or Highway 30.