First Quantum Minerals has reduced ore processing at its sprawling copper mine in Panama as weeks-long protests against the project is blocking access to the port, the Canadian miner said on Monday.
The new contract for the Cobre Panama mine, which contributes one per cent to global copper production, was approved on Oct. 20. However, the agreement has faced numerous legal challenges due to protests that claim it favors the miner too much and allege corrupt practices in its approval.
The company has denied all allegations but the uncertainty has triggered a 45 per cent drop in its shares since the new contract, through Friday’s close. They fell another 4.3 per cent on Monday.
First Quantum said it had ramped down operations at one ore processing train as the blockade at the mine’s Punta Rincon port has affected the delivery of supplies for its on-site power plant and is impacting the loading of copper concentrates.
The reduction of ore processing could impact about two per cent of Panama’s national workforce, the company said, adding two ore processing trains remain operational.
Get daily National news
A Reuters survey earlier in November found that a majority of lawyers believe that Panama’s top court would revoke First Quantum’s contract for the mine, which contributes five per cent to the company’s gross domestic product.
The mine would need to reduce the purchase of supplies and services that are equivalent to US$20 million in weekly revenues to more than 2,000 Panamanian companies if the stoppages continue, the company added.
- Gisèle Pelicot’s ex-husband gets 20 years after guilty verdict in rape trial
- ‘Drunk’ cruise passenger dies aboard ship after allegedly assaulting staff
- Student, teacher killed in Wisc. school shooting identified, motive still unclear
- Putin boasts Ukraine gains, says Russia ready for missile ‘duel’ with West
Comments