Advertisement

Enbridge says costs of Line 3 replacement will be higher than original estimate

Enbridge company logos on display at the company's annual meeting in Calgary, Thursday, May 12, 2016.
Enbridge company logos on display at the company's annual meeting in Calgary, Thursday, May 12, 2016. THE CANADIAN PRESS/Jeff McIntosh

Enbridge Inc. says the cost of its Line 3 replacement project has risen nine per cent from its original estimate when it was sanctioned in 2014.

The company now estimates it will cost $5.3 billion for the portion in Canada and US$2.9 billion in the United States to replace the pipeline that runs from Hardisty, Alta., to Superior, Wisc.

It attributed the higher cost to delays in the regulatory process and route modifications, among other changes.

However, the company said the impact of the increased costs on project returns are expected to be offset by lower operating costs and a strong U.S. dollar.

Financial news and insights delivered to your email every Saturday.

Enbridge said it expects to start construction in Canada this summer and have the pipeline in service in the second half of 2019.

Story continues below advertisement

The announcement came as Enbridge reported a second-quarter profit of $919 million or 56 cents per diluted share compared with a profit of $301 million or 33 cents per diluted share a year ago when the company had fewer shares outstanding.

Adjusted earnings for the quarter amounted to $662 million or 41 cents per share, up from $456 million of 50 cents per share a year ago.

Sponsored content

AdChoices