A controversial pulp mill in northern Nova Scotia is facing delays with its new wastewater system, making it likely to miss the provincial deadline of January 2020 to stop using a polluted lagoon.
The Northern Pulp mill has been sending untreated effluent to a First Nation reserve for more than half a century, something the province’s former environment minister called one of the worst cases of environmental racism in Canada.
READ MORE: Northern Pulp mill confirms effluent leak near Pictou Landing
Under provincial legislation, the kraft pulp mill has less than 15 months to overhaul how it processes wastewater.
Kathy Cloutier, a spokeswoman for Paper Excellence Canada, which owns the Abercrombie Point mill, says the setback is due to a delay with a pipeline.
WATCH: Blockade of Northern Pulp Mill continues
She says the new wastewater treatment facility will meet the deadline, but that a new outfall discharge pipe will take longer.
Despite the delays, Cloutier says once the new treatment plant is operational, untreated effluent will no longer leave the mill.