TORONTO – Bombardier’s rail division says Ontario’s GO Transit system will be getting 125 additional two-level commuter rail cars to be produced over a two-year period at its factory in Thunder Bay, Ont.
Bombardier valued the order at C$428 million (US$328 million).
READ MORE: Delays and crowding on commuter GO Train spark commuter complaints
Production of the bilevel rail cars is scheduled to start in the northwestern Ontario city in the second quarter of 2018, and final delivery is scheduled for the first quarter of 2020.
The Montreal-based company announced the order from Berlin, Germany, where its Bombardier Transportation rail equipment business has its global headquarters.
READ MORE: Union Pearson Express ridership doubles on first day of reduced fares
The order is the result of a conversion of purchase options held by Metrolinx, the Ontario government’s regional transportation agency for the Toronto and Hamilton areas.
Bombardier says the cars have been deployed or ordered for transit authorities in 14 metropolitan regions across Canada and the United States.
READ MORE: TTC demands Bombardier apologize to riders after streetcars delayed yet again
In April, Bombardier announced it’s cut by more than half the number of streetcars it had promised to deliver to the Toronto Transit Commission this year, the latest in a string of delays that’s angered the TTC, city council and Mayor John Tory.
Bombardier was supposed to have delivered almost 70 new streetcars to Toronto by now, but the TTC has only 17. The TTC is applying for damages under the terms of its contract with Bombardier, and is still determining whether to sue the company.