Engineers approve plan to begin removal of Halifax crane toppled by Dorian

Click to play video: 'Work to remove Halifax crane toppled by Dorian begin this weekend'
Work to remove Halifax crane toppled by Dorian begin this weekend
WATCH: Nova Scotia’s Labour minister says work will begin this weekend to remove a huge construction crane that collapsed in Halifax during Hurricane Dorian. Jesse Thomas has more. – Sep 13, 2019

Nova Scotia’s Labour minister says work will begin this weekend to remove a huge construction crane that collapsed in Halifax during Hurricane Dorian.

Labi Kousoulis says a structural engineering report has been completed and approved by his department and Halifax Regional Municipality Fire Department.

The twisted, yellow structure is draped over a building that was under construction in the city’s downtown.

READ MORE: New Nova Scotia Power training tool aimed at preventing slips, trips and falls

Video posted on social media showed the dramatic collapse at the height of the heavy rain and high winds Sept. 7.

Kousoulis said Friday the first work this weekend will see crews going from floor to floor to shore up the building in case it has been compromised.

Story continues below advertisement

“Posts will be put in place to ensure the building doesn’t fall in case there’s any compromised columns in it,” he told a news conference at his constituency office in Halifax.

A drone belonging to Halifax Regional Fire and Emergency could be seen flying around the building Friday to assist crews in their assessment.

“They will then pin the crane to the building. They will strap the crane to the building so as they start dismantling it, it doesn’t come apart under itself,” he said.

READ MORE: Some valley residents still without power nearly a week after hurricane Dorian

Then a portable crane will be brought in to begin removing the damaged crane piece by piece.

Kousoulis said the work should take about two weeks, depending on the weather or any problems.

“The top part of the crane resting on the building is 67,000 pounds. You are dealing with a lot of steel and a lot of weight. That is essentially what the challenge is,” he said.

The minister said the crane collapse could have been much worse, but fortunately it fell on the only unoccupied space possible and no one was hurt.

READ MORE: Rural N.S. residents providing support to each other in Dorian aftermath

“It’s amazing the angle it fell. We were fortunate because any other way the crane fell, it would have been bouncing off occupied buildings. It would have been on the street.”

Story continues below advertisement

Kousoulis said he’s confident other construction cranes on the Halifax skyline are safe, but inspections will be done as a precaution.

He said some developers have taken it upon themselves to have inspections done by independent engineers.